Del Prado construction will kick into high gear over the next couple weeks in order to prepare for the switch to two-way traffic. The latest phase of construction is part of the city of Dana Point’s PCH/Del Prado Streetscape Improvement Project in the Lantern District

According to City Engineer Matthew Sinacori (via the city’s weekly updates), the upcoming construction projects, listed below, will take place through Oct. 2, although weather or unforeseen issues may impact the schedule.

Intersection crosswalk pavers should be completed by the end of this week, despite the rain slowing the process. Cobble paving in the Golden Lantern median near PCH will also be completed. Del Prado’s asphalt seal coat will be placed over the entire roadway during the week of Sept. 21.

During that same week, the city will begin to correctly orient traffic on Del Prado and complete striping work to allow for the conversion to two-way traffic. The switch to two-way is planned to occur between Sept. 28 and 30.

Work is also being scheduled to complete The Lantern District archway. Concrete banner poles on Pacific Coast Highway between Del Prado and Ruby Lantern are set to be installed in October.

To subscribe to construction alerts, email ssharke@danapoint.org. Contact Sinacori at 949.248.3574 or msinacori@danapoint.org for more information.

Construction Alert Sept 15 2015