Beginning Monday, Nov. 7 construction for the Dana Point Harbor revitalization project is scheduled to work on concrete pathway drains, conduit for traffic signals and more.

The placement of aggregate base and asphalt will take place on Pureto Place, south of Dana Point Harbor Drive.

There will also be construction of two concrete parkway drains and the placement of asphalt concrete at Casitas Place.

The installation of conduit for traffic signals at Dana Point Harbor Drive and Casitas Place are planned as well as the the installation of two inch water service on Casitas Place.

The construction is scheduled from Monday, Nov. 7 to Friday Nov. 18 from 7 a.m.-3:30 p.m.

County officials said the schedule is tentative and may change depending on weather and other factors.

For more information, or to speak with a representative, call Paul Weaver at 714.719.1742. For more information about the overall project, visit www.ocdph.com/revitalization, or call 949.923.2236.

About The Author Dana Point Times

comments (0)

Your email address will not be published.

You may use these HTML tags and attributes: <a href="" title=""> <abbr title=""> <acronym title=""> <b> <blockquote cite=""> <cite> <code> <del datetime=""> <em> <i> <q cite=""> <s> <strike> <strong>